Sheringham is open for business

Free parking offered at Morris Street car park

Find out about the new sandscaping solution

Bacton to Walcott coastal management scheme logo

The beaches in front of Bacton Gas Terminal and the villages of Bacton and Walcott will be transformed during summer 2019 as a result of the Sandscaping scheme.

A UK-first multi-partner project, the scheme will see approximately 1.8 million cubic metres of sand placed and engineered on these beaches. The height and width of the beaches will be significantly increased and access to beaches improved.

Briefly this will involve the following works over Summer 2019:

Bacton & Walcott Sandscaping - Film 1 from Chris Taylor Photo / AeroVisuals on Vimeo.

 

July to August 2019

Sandscaping work. Sandscaping involves using a large production vessel (ship) to pump sand to the beach. The sand is then positioned using bulldozers with GPS. Whilst the contractor has made every effort to minimise and will be monitoring noise from plant working on the beach, you may notice some noise as this work continues around the clock.

Sandscaping work will progress quickly, starting at Bacton Gas Terminal and working towards Walcott. As the beaches towards Bacton village and Walcott are nourished, sections will be closed for public use and then reopened as soon as possible.

If you are in the area why not pop down to the Sandscaping visitor unit on Walcott seafront. The unit is open daily from noon to 5pm.

The below plan indicates approximate timings of sand nourishment along the frontage. Week 1 began on July 12. 

May to June 2019

The beach at the villages of Bacton and Walcott will be open as usual. While work is carried out at the Bacton Terminal constructing a new replacement outfall pipe the beach in front of the Terminal will have limited access. A pathway around the working area to provide a route to Mundesley, will be available whenever possible.  Weekly breeding bird surveys are taking place with diligent monitoring of active colonies, active burrows and bird behaviour. Recent surveys have been published and can be accessed via the links below.

Pre-work survey
Early June
Mid June
Early July
Mid July

Across the Bacton frontage, sand martin colonies are located in relatively discreet sets of burrows.  In the initial survey work, five colonies were identified in burrow sets: one near the access ramp to the south; two in the middle of the Bacton Gas Terminal frontage; and two located to the north (on the edge of the intended sand placement zone).  A new colony (with associated fresh burrows) has now been established adjacent to the colonies to the north of the site.  These six colonies have been surveyed weekly, based on a one hour watch per colony.  The tabulated figures are based on the number of active burrows (not birds) in that colony.  As we approach the middle of the survey period (which runs until completion of the sand placement), it should be noted that fluctuations in numbers (week on week) may be in response to the time of day for that particular burrow, weather conditions and also the stage in the breeding cycle.  Based on the breeding cycle. activity around burrows can increase/decrease in response to the status of eggs or young.  Overall, the trend across the frontage has been an increase in active burrows in existing colonies and the creation of new burrows (in both existing colonies and the “new” colony). 

Find out more about the project below in the spring - summer 2019 update and visit our regularly updated Sandscaping FAQs page.

Also, the following video outlines the Bacton to Walcott Coastal Management Scheme which is designed to protect Bacton Gas Terminal and nearby villages of Bacton and Walcott by raising beach levels. 

The following storymap gives more detail about the scheme. View in full screen.

The Bacton to Walcott planning application page contains information concerning the decision making process and those who were consulted during the planning stages of this project.